Page 1 of 1

ETA on B16 revisions, and delivery

PostPosted: Sun Jul 14, 2013 9:58 am
by crtstudios
Just wondering if there is a rough idea when the B16 will be revised, and shipping again, and what adjustments have been made. Thanks!

Re: ETA on B16 revisions, and delivery

PostPosted: Thu Jul 18, 2013 9:41 am
by agershon
Lead time is down to 1-2 weeks (from 3-4 weeks more recently).

Do you know there are revisions coming?

Re: ETA on B16 revisions, and delivery

PostPosted: Thu Jul 18, 2013 10:21 am
by crtstudios
I bought one several months ago, and was told it was on backorder for revisions. That's about all I know. I'm just looking for a realistic estimate on when I might get mine in my mail box.

Re: ETA on B16 revisions, and delivery

PostPosted: Thu Jul 18, 2013 10:53 am
by agershon
Ok, interesting. I got one a couple months back and recently completed the build. Was planning on buying another but noticed they're on backorder. Guess we'll just have to see.

Re: ETA on B16 revisions, and delivery

PostPosted: Thu Jul 18, 2013 11:33 am
by crtstudios
Yeah. I guess so.

Re: ETA on B16 revisions, and delivery

PostPosted: Mon Jul 22, 2013 9:03 am
by tpryan
Boards should be back in stock in about a week.

Re: ETA on B16 revisions, and delivery

PostPosted: Mon Jul 22, 2013 9:26 am
by agershon
tpryan \$m[1]:Boards should be back in stock in about a week.


Thanks Tim. Are the boards revised or did you simply run out of stock?